L'attente que le béton sèche
A building project is typically handled in a series of stages, each with its own manager. The goal is always to hand off each stage from one manager to the next without delays. But when moisture-sensitive flooring is involved, one part of the job can throw a wrench in the process: the concrete slab.
What’s Required for a Successful Flooring Installation?
For a flooring installation to be successful:
- The slab’s niveaux d'humidité et de pH need to be within the acceptable range.
- The slab must be protected from outside moisture.
- The slab’s moisture level must be compatible with both the specified floor covering and the flooring adhesive.
- The potential for moisture emission from the slab must be addressed.
What Factors Delay a Slab’s Drying Time?
Many industry standards guide how a concrete slab is placed and dried, but the drying time for any slab is almost impossible to predict. The factors that affect drying time are unique to each installation. They include:
- The components of the original concrete mix
- Humidité de l'air ambiant
- Conditions finales de service
- Finitions de surface
- How well the HVAC system is working
- Pratiques flottantes ou remouillage
When any of these factors change during the project, the concrete may need more time to dry. Delays in getting a properly dried slab can throw off the entire construction schedule.
Vaut-il mieux attendre que la dalle sèche ou continuer ?
Lost labor hours and added costs are two results of schedule interruptions on a construction project. But the alternative, pushing ahead despite the slab’s condition, risks flooring failure. A moisture-related flooring problem is a no-win situation for everyone involved, from contractors and construction managers to flooring installers, adhesive manufacturers, and facility owners. Experience shows that installing flooring before the slab’s moisture issues are resolved costs far more than waiting and getting it right the first time.
Tous les yeux sont rivés sur le but, pas sur la montre
The ultimate goal of a construction project is an installed flooring system that stays problem-free for the long term.
When the construction schedule leaves no room to deal properly with moisture in the concrete, there’s a temptation to rush the project, and that invites flooring failure.
Téléchargement gratuit – 4 raisons pour lesquelles votre béton met une éternité à sécher
Comment savoir quand la dalle est prête
Some methods, such as desiccant drying and surface treatments, can help speed up drying. But how can the flooring contractor be sure the slab’s moisture level is compatible with the moisture-sensitive adhesive and flooring on the project?
Mesurer avec précision relative humidity (RH) within the slab is the best way to know when the slab has dried enough.
Surface-only indicators of a slab’s moisture condition, such as calcium chloride testing, aren’t reliable, even though they have been widely used in the industry.
In-situ RH testing is better than surface-only testing because it reflects the RH conditions the slab will reach under an installed floor. With accurate knowledge of the slab’s RH, the general contractor and flooring installer will know whether to allow more drying time to meet the adhesive and flooring specifications, or to choose a different adhesive or flooring product that’s compatible with the slab’s current condition. RH testing gives everyone on the project the information they need to decide whether to wait or move on to the flooring installation.
Jason possède plus de 20 ans d'expérience dans la vente et la gestion des ventes dans un large éventail de secteurs et a lancé avec succès une variété de produits sur le marché, notamment les premiers tests d'humidité du béton Rapid RH®. Il travaille actuellement chez Wagner Meters en tant que responsable des ventes de produits Rapid RH®.
Dernière mise à jour le 9 octobre 2026
Ils ont coulé mon béton pour mon trottoir. La température était d'environ 40 degrés, le ciment était aqueux, donc il n'a pas pu le faire durcir. Il faisait sombre lorsqu'il est parti. Est-il possible qu'il revienne le lendemain pour le finir ??? Il n'arrêtait pas de dire qu'il avait tout gâché !! Je suis sorti à 3 heures du matin, je me sens plutôt bien, car il pourra revenir demain et mettre le dessin en place. Peut-il faire ça ???
Gerrie :
Merci pour le commentaire. Je n'ai jamais entendu dire que cela soit une possibilité réaliste. En général, le béton a durci à un point tel qu'une finition correcte ne serait pas possible. Bonne chance.
Nous construisons une nouvelle construction et je souhaite des sols en béton poli. Mon constructeur me dit de poser d'abord du stratifié car il faut beaucoup de temps pour que la dalle sèche à Naples, en Floride, et il y aura plus de fissures. Avez-vous des conseils ? Je ne veux pas attendre et je suis prêt à faire réparer les fissures. Est-ce une bonne idée ?
Judith :
Merci pour le commentaire. Je ne peux pas dire que j'aie jamais entendu parler du processus de laminage puis de polissage du béton. Je demanderais conseil à une entreprise de votre région qui s'occupe spécifiquement du polissage du béton. J'ai fait une recherche rapide sur Google et il semble y en avoir quelques-unes dans la région de Naples.
Salutations,
Jason
Mon constructeur a chargé 15 palettes CMU sur les fondations 20 heures après le coulage.
Est-ce un problème ou utilisent-ils du ciment à durcissement rapide ?
Merci.
Bob
Bob:
Merci pour la question, mais ce n'est pas vraiment une question à laquelle je peux répondre. Bonne chance.
Jason